Agile Project Time Planning
- Protect time by aggregate time buffer
- Aggregate components into groupings and look at dependancies of groupings
- Critical Path - longest path through real time required for a single chain of dependent tasks to complete in order
- 'Eventually everything hits the CP' -- Goldratt
- Components not tasks
- PERT chart for parallel development
- Resource constraints - specialists need to be added to PERT
- Samples --http://whatis.techtarget.com/definition/0,,sid9_gci331391,00.html