Wideband Delphi for additional time estimates
- Kickoff meeting - At least three people meet to discuss project and components
- Estimation - each person makes three estimates - most likely, optimistic, pessimistic
- Meeting: give estimates to facilitator and discuss without revealing identities
- Repeat steps 2 and 3 at least once
- Take averages of final cycle estimates
- Calculate final estimate: Optimistic + Pessimistic + 4* Most Likely/6
- Calculate likely deviation: Pessimistic - Optimistic / 6